Two one-sentence sections of the Contractors State License Law cover a contractor who stops working on a job and a contractor who spends a job’s money somewhere else. Bus. & Prof. Code s. 7107 makes abandonment a cause for disciplinary action, and s. 7108 does the same for diversion of funds. Neither has been amended in decades: s. 7107 dates from 1939, and s. 7108 was last amended in 1959.
Abandonment: s. 7107
The whole section is one sentence:
Abandonment without legal excuse of any construction project or operation engaged in or undertaken by the licensee as a contractor constitutes a cause for disciplinary action.
Two limits are in the wording. The abandonment has to be “without legal excuse”, and the section does not list what counts as one. And the project has to be one “engaged in or undertaken by the licensee as a contractor”. Beyond that the section reaches “any construction project or operation”, with no floor on the size of the job.
Diversion: s. 7108
Section 7108 names three acts, any one of which is cause for disciplinary action:
- diverting funds or property received “for prosecution or completion of a specific construction project or operation”;
- diverting funds or property received “for a specified purpose in the prosecution or completion of any construction project or operation”; and
- “failure substantially to account for the application or use of such funds or property on the construction project or operation for which such funds or property were received.”
The first two are about where the money went: funds or property received for one project, or for one purpose on a project, and used for something else. The third is about records. Failing substantially to account for how a project’s funds or property were used on that project is a ground of its own, separate from diverting them.
What the board does about them
The registrar has two tools for either ground.
A citation. Under s. 7099, the registrar may issue a citation instead of starting a disciplinary proceeding, with an order of correction, an order to pay a sum to the injured party in lieu of correction, or a civil penalty. Since July 1, 2026, when s. 7099.2 became operative, that penalty is “not less than five hundred dollars ($500) nor greater than eight thousand dollars ($8,000)” except where the chapter provides otherwise; the higher tier of $1,500 to $30,000 is for ss. 7110, 7114 and 7118, not for ss. 7107 or 7108. The 16 CCR s. 884 table as the CSLB Law Book 2026 reprints it still shows the figures from before July 1; the July 2026 fine changes post has the before and after.
A disciplinary action against the license. CSLB’s Disciplinary Guidelines, incorporated into 16 CCR s. 871 in their revision of December 11, 1996, give the same range for both sections:
| Section | Minimum penalty | Maximum penalty | Among the terms listed “If warranted” |
|---|---|---|---|
| 7107, abandonment | Revocation, stayed, 3 years probation | Revocation | absent compelling mitigating circumstances, an actual suspension of at least 30 days; restitution |
| 7108, misuse of funds | Revocation, stayed, 3 years probation | Revocation | absent compelling mitigating circumstances, an actual suspension of at least 30 days; outright revocation where the diversion is for personal use not related to construction work; restitution |
Section 871 lets the board depart from the guidelines where the facts of a case warrant it, and the guidelines say every license disciplined, stayed or not, has to post a disciplinary bond under s. 7071.8.
Arbitration instead of discipline
Section 7085 lets the registrar, with the agreement of both the licensee and the complainant, refer a complaint to arbitration. It names six sections, ss. 7107, 7109, 7110, 7113, 7119 and 7120, and adds “any complaint arising from a contract involving works of improvement”. Abandonment is on the named list; s. 7108 is not. The registrar also has to find, among other things, that the complainant has suffered or is likely to suffer material damages, that the licensee has no history of repeated or similar violations, and that the parties have not already agreed to private arbitration, and that the public interest would be better served by arbitration than by disciplinary action.
The homeowner’s side
The contractor’s bond is one place a homeowner left with an unfinished or unpaid-for job can look. Section 7071.5 makes the bond for the benefit of, among others, a “homeowner contracting for home improvement upon the homeowner’s personal family residence damaged as a result of a violation of this chapter by the licensee”, and of a person damaged by a willful and deliberate violation or by the licensee’s fraud in performing a construction contract.
A criminal case is a different track. The Anchored Tiny Homes post covers felony charges, which are allegations and not findings, filed after consumer complaints that alleged abandoned projects and homeowners’ money not used on their own projects. Sections 7107 and 7108 are grounds for the registrar to act against a license, whatever happens in court.
Two other sections numbered 7107 and 7108
The Public Contract Code has its own s. 7107, and it is about something else: on a public work, the public entity releases retention within 60 days after completion, and the original contractor pays each subcontractor its share within seven days of receiving it. Public Contract Code s. 7108 is about train service contracts. Keep them apart by subject: walking off a job and misusing its money are the Business and Professions Code sections, and retention on a public work is the Public Contract Code one. In this site’s practice sets, abandonment sits in Contract Requirements and Execution, diversion in Business Organization and Licensing, and retention release in Public Works.
Sources
- Contractors State License Law, Business and Professions Code, ss. 7071.5, 7085, 7099, 7099.2, 7107 and 7108
- CSLB rules, 16 CCR s. 871 (Disciplinary Guidelines, rev. 12/11/96)
- Public Contract Code, ss. 7107 and 7108